Silver Lake Storage Replacement

Contractor of Choice
Mladen Buntich Construction Co. was contracted by the The Los Angeles Department of Water & Power (LADWP). LADWP was building a new Reservoir Storage Facility at the Headworks spreading grounds, a 43-acre site adjacent to the Los Angeles River and between the City of Burbank and Griffith Park.
In January 2006, the United States Environmental Protection Agency (EPA) promulgated the Long Term 2 Enhanced Surface Water Treatment Rule and the Stage 2 Disinfection and Disinfection Byproducts Rule. These regulations established stringent requirements for protecting drinking water supplies from contamination and disinfection-related risks.
In response to these requirements, the Los Angeles Department of Water and Power (LADWP) determined that its open reservoirs were no longer suitable for continued potable water storage because of their exposure to environmental contaminants. To achieve regulatory compliance, the reservoirs would need to be covered, treated prior to use, or removed from service. As a result, the Silver Lake and Ivanhoe Reservoirs were taken out of potable water service and replaced with two underground reservoirs and a large-diameter pipeline system at the Headworks property.
The new below-grade storage system consists of two facilities: the Headworks East Reservoir and Headworks West Reservoir. The project also incorporated a four-megawatt hydroelectric power plant designed to harness energy from the flowing water. In addition, the site was transformed through ecosystem restoration efforts that incorporated environmental habitats and recreational amenities for community use.
Mladen Buntich Construction Co. was awarded 2 contracts in the beginning of 2013 for providing services for the procurement, installation, and backfill of 18-inch to 96-inch welded steel pipe for the inlet, outlet, drain, and overflow piping and storm drain. In addition to the new utility installation, Buntich installed the deep access shafts for the tunneling work with a beam and plate shoring system.
In early 2013, Mladen Buntich Construction Co. was awarded two contracts to provide procurement, installation, and backfill services for 18-inch to 96-inch welded steel piping. The piping systems included inlet, outlet, drain, overflow, and storm drain facilities. In conjunction with the new utility installation, Buntich also constructed deep access shafts required for the tunneling operations using a beam-and-plate shoring system.
Project Features Include:
- Phased Construction: The project was completed through four major phases.
- Phase I: Construction of the Headworks East Reservoir, valve vaults, associated site piping and grading, River Supply Conduit 1A East, and the tunnel section.
- Phase II: Construction of the Headworks West Reservoir.
- Phase III: Construction of River Supply Conduit 1A West, the hydroelectric power plant, and regulating station.
- Phase IV: Ecosystem restoration and enhancement of the overall project site.